Grid connection plans for 2025
In 2025, it is planned to carry out grid connection for the energy supply of large projects that are currently underway. These projects are of particular importance both for the regions where they are situated and for the country as a whole. These include:
- Construction of the Adler Bypass motorway as part of the project to build a new highway between Goryachy Klyuch and Adler, which will serve as a high‑speed alternative to the A‑147 motorway between Dzhubga and Sochi. The requested power capacity is 16.6 MW The customer is Rossiyskiye Avtomobilnye Dorogi, a state‑owned company. The cost of grid connection is RUB 1.6 billion.
- Grid connection of solar power plants in the Seversky District of the Krasnodar Krai. The applicant is Vozobnovlyaemyye Istotnye Energii LLC (Hevel Group). The total capacity is 40.5 MW. The total cost of the grid connection contracts signed is RUB 762.6 million.