Completion of grid connection agreements
During the reporting year, the Company completed 37,433 grid connection contracts. The total capacity of the completed grid connection agreements was 772 MW (17% above the target).
Connection categories | Number of completed grid connection agreements | |
---|---|---|
– | Total power (MW) | |
Up to 15 kW inclusive, total | 34,817 | 415.1 |
Over 15 kW to 150 kW inclusive | 2,166 | 132.9 |
Over 150 kW and up to 670 kW | 186 | 45.7 |
At least 670 kW | 96 | 170.4 |
Power generation facilities | 80 | 4.4 |
Temporary connection | 88 | 3.3 |
Total | 37,433 | 771.8 |
Applicant | Facility | Connected capacity (MW) |
---|---|---|
RZD JSC | Grid connection of traction substation | 12.2 |
Caspian Pipeline Consortium — R JSC | Grid connection of consumer terminals of the oil pipeline system (offshore terminal, tank farm and onshore facilities) | 10 |
Specialised Developer Garantiya LLC | Grid connection of consumer terminals of a multi‑storey residential complex in the central inner‑city district of Krasnodar | 5.0 |
Kopanskoy Industrial Park Management Company LLC | Grid connection of consumer terminals of a land plot for agricultural use | 5.0 |
Rostelektroseti LLC | Grid connection for power supply to consumer terminals on a land plot for the construction of social and business buildings and structures of the second phase of the German Village residential complex in the Prikubansky intra‑city district of Krasnodar | 5.0 |
Federal State Institution Taman Federal Highway Administration | Grid connection of consumer terminals for the needs of a new high‑speed highway to the crossing across the Kerch Strait (stage 1, sub‑stage B, stage 2) | 4.6 |
Specialised Developer YugStroyImperial LLC | Grid connection of consumer terminals for multi‑storey residential buildings in Znamensky settlement | 4.2 |
Ober Khutor LLC | Grid connection of consumer terminals in a hotel complex in the Adler district of Sochi | 4.0 |
As part of the Federal Trunk Network Development project, which is part of the Safe and High‑Quality Roads national project, there was a power supply set up for the new A‑289 four‑lane motorway, which is about 130 km long. This route provides a long‑distance approach to the Crimean Bridge, bypassing the city of Slavyansk‑on‑Kuban. We built three high‑voltage power supply centres with a voltage rating of 35–110 kV, as well as over 119 km of PTLs with a voltage rating of 10–110 kV. The facility is provided with nearly 5 MW of capacity.
For the third consecutive year, the Company has been supplying electricity to electric vehicle charging stations as part of the project to implement the Concept for the Development of Electric Vehicle Production and Use in the Russian Federation. In 2024, the Company completed the grid connection of 24 charging stations with a total capacity of 3.6 MW, located in large settlements of the Krasnodar Krai and the Republic of Adygeya, as well as on regional roads.
As part of the regional programme on the upgrade of primary healthcare, the Company took steps in 2024 to ensure that over 40 healthcare facilities could be connected to the power grid. These include six outpatient clinics, 15 paramedic and midwifery stations, and 22 hospital’s outpatient departments (five of which are children’s polyclinics). The total capacity exceeded 4 MW.
Russia’s southern regions have historically played a significant role in the nation’s food supply. During 2024, the Company completed the grid connection of over 600 agricultural and food industry enterprises with a total capacity of 38 MW. Among the most notable facilities are agricultural land plots of Uchastie Krestiyanskoye Hozyaystvo LLC for 1.5 MW (Novokubansky District), Tkacheva Agrokompleks JSC for 0.9 kW (Dinskoy District) and Kalinin Selskokhozyistvennaya Kompaniya OJSC for 3 MW (Gulkevichesky District).
Over the past few years, the Krasnodar Krai and the Republic of Adygeya have been particularly attractive destinations for migrants. This trend naturally leads to increased demand for housing. To meet the demand, the Company allocated electric capacity to cover over 2,000 housing projects, with a total capacity of 166 MW.
Over 30 socially important facilities, such as schools, preschools, cultural institutions, and sports facilities, with a total capacity of over 2.5 MW, were connected to the power grid. In particular, capacity was provided for the new Sambo Palace sports arena in the Prikubansky District of Krasnodar, as well as for a new 1,000‑strong school in Maykop, Republic of Adygeya. The grid connection of the school was accomplished while setting up the power supply for a large residential area in the southern part of the city, which includes multi‑storey buildings, amenities, transport and engineering infrastructure.